← All suppliers
WORLEY PTE. LIMITED
- Wins
- 7
- Total value
- S$6.7M
- Median value
- S$2K
- First / last win
- 8 Mar 2022 – 7 Apr 2025
Agencies served
- Energy Market Authority of Singapore5
- Housing and Development Board1
- Sentosa Development Corporation1
Award history
| Date | Description | Agency | Amount |
|---|---|---|---|
| 7 Apr 2025 | PROVISION OF TECHNICAL ADVISORY SERVICES FOR CROSS-BORDER CARBON CAPTURE AND STORAGE PROJECT FOR TWO YEARS WITH OPTION TO EXTEND BY ANOTHER ONE YEAR (EMA-ITT- 2024-0063) | Energy Market Authority of Singapore | S$573 |
| 28 Oct 2024 | PERIOD CONTRACT TO ADVISE ON TECHNICAL MATTERS PERTAINING TO POWER STATION DESIGN, DEVELOPMENT AND OPERATION (EMA-ITT-2024-0016) | Energy Market Authority of Singapore | S$1,610 |
| 7 Nov 2023 | Specialist Consultancy Services for the Environmental Monitoring and Management Plan for the Infilling Works (Phase 4) | Housing and Development Board | S$5,999,880 |
| 16 Feb 2023 | ENVIRONMENTAL FEASIBILITY STUDY FOR SENTOSA | Sentosa Development Corporation | S$670,609 |
| 7 Jun 2022 | Period Contract for Consultancy Services to Advise on Technical Matters Pertaining to Gas System Network and Infrastructure | Energy Market Authority of Singapore | S$2,515 |
| 31 Mar 2022 | RETAINER SERVICE TO INVESTIGATE ELECTRICITY GENERATING PLANTS, ELECTRICITY TRANSMISSION/DISTRIBUTION NETWORK EQUIPMENT, GAS FACILITIES/PLANTS AND GAS TRANSMISSION/DISTRIBUTION NETWORK EQUIPMENT OUTAGES | Energy Market Authority of Singapore | S$1,606 |
| 8 Mar 2022 | RETAINER SERVICE FOR CONSULTANCY SERVICES ON TECHNICAL AND ECONOMIC ASSESSMENT OF POWER GENERATION EQUIPMENT | Energy Market Authority of Singapore | S$1,025 |