Wins
4
Total value
S$18.9M
Median value
S$5.1M
First / last win
21 Feb 2022 – 8 Apr 2025

Agencies served

  • Public Utilities Board4

Award history

DateDescriptionAgencyAmount
8 Apr 2025Maintenance of Crest Gate System at Marina BarragePublic Utilities BoardS$7,811,000
24 Jan 2025Partial Replacement of Seawater Reverse Osmosis Membranes at Tuas South Desalination PlantPublic Utilities BoardS$895,488
21 Feb 2022Maintenance of Crest Gate System at Marina BarragePublic Utilities BoardS$6,886,000
21 Feb 2022Maintenance of Engine-Generator System at Marina BarragePublic Utilities BoardS$3,275,000